The punch list guide: what it is, who owes what, and how to close it out
By Ilya Vidyaev, superintendent · Updated
A punch list is the last stretch of a job, and it is where schedules slip and relationships get tested. This guide covers how it works on a typical US or Canadian project, in the order you will meet it. Contracts differ. Where a point depends on yours, the guide says so.
What is a punch list?
A punch list is a written list of small items that are unfinished, damaged or not built to the plans at the end of a construction job. Each item names where it is, what is wrong and who has to fix it. The work is not closed out until every item is done and checked.
You walk the work, write down what is not right, and track each item until it is fixed. That is the whole idea.
A punch list is for finish-level problems. A scratched door, a missing outlet cover, a paint touch-up, a drawer that rubs. It is not the place for work that is largely undone or for design changes. Those belong in other documents.
On a big job there may be a list for every trade, every floor or every unit. On a small job it may be a single page. The purpose is the same: one agreed record of what is left.
When does the punch list happen, and how does it relate to substantial completion?
The punch list is usually made near the end of the job, around substantial completion. Substantial completion generally means the owner can use the space for its intended purpose, with only minor work left. The punch list is that minor work. Final completion comes once it is finished. Your contract defines both terms.
Most teams walk more than once. An early walk finds problems while trades are still on site and can fix them fast. A later walk, when the space is nearly ready, builds the list the owner signs off on.
Substantial completion is a contract term, and the exact definition varies. It is often tied to an inspection, an occupancy approval or a certificate from the architect. Read the definition in your contract before you promise a date to anyone.
Final completion is the next milestone. It usually means all punch list work is done, the closeout paperwork is delivered and the job can be fully paid. Again, your contract sets the conditions.
A useful rule: do not let the list grow after the walk without saying so. Add new items with a date, so everyone can see what was on the original list and what came later.
Who is responsible for punch list items?
The subcontractor who did the work is usually responsible for fixing it, at its own cost. The general contractor, usually through the superintendent, runs the list and checks the fixes. The owner and architect may add items or review the list. Your contract decides who inspects and who has the final say.
General contractor and superintendent. They own the process. They organize the walk, write up the items, send each one to the right trade, chase the fixes and check the result. They answer to the owner for the whole job, so an open item is their problem even when a sub caused it.
Subcontractors. Each sub is usually responsible for correcting its own defective or incomplete work. Subcontracts usually say so. The cost of a fix generally stays with the party who caused the problem.
Owner. The owner often walks the space and may add items. The owner may also have to accept the work in writing. Items the owner adds late are a common source of arguments, so date them.
Architect or design professional. Many contracts give the architect a role in inspecting the work and confirming it matches the plans. Some architects issue their own list. If yours does, fold it into the one master list so nothing lives in two places.
When it is unclear whose work an item is, decide quickly and write down the decision. A defect that bounces between two trades gets fixed by neither.
How do you run a punch list walk?
Walk the space room by room, in the same order every time. Look at each surface and each system in that room. Write one line for each problem, take a photo of it and record exactly where it is and which trade owns it. Finish one room before you start the next.
Prepare first. Bring the plans, the finish schedule and a way to take photos. Make sure the space is clean and well lit. Poor light hides defects, and you will only find them later.
Use a fixed order. Start at the door, work clockwise, and check the ceiling, walls, floor and fixtures in each room. A fixed order means you skip nothing and anyone can pick up where you left off.
One trade per line. If a wall needs paint and the outlet beside it is crooked, that is two items for two trades. Splitting them lets each sub close its own work.
Take a photo of every item. A photo settles arguments about what was meant. Include enough of the room to show where it is, and a closer shot of the problem.
Record the location. Use the same room names as the plans. A floor, a room and a spot in the room, such as the north wall by the window, is enough for someone to find it cold.
Walk with the people who need to hear it. If the owner or architect joins, agree on the list before you leave the room, not after.
How do you write a good punch list item?
A good punch item says where the problem is, what is wrong, what is expected instead and who owns it. Keep it to one problem per item, with a photo. Someone who was not on the walk should be able to find it, understand it and fix it without calling you.
Compare two versions. Vague: "Fix kitchen." Better: "Kitchen, north wall above range. Drywall seam shows in raking light. Needs another coat, sanded and repainted." Owner: drywall, then paint. The second one can be done without a phone call.
Say what is wrong, not how to fix it. You usually do not need to tell a trade how to do its job. You need to say what the finished work should look like.
Point to the standard when there is one. If the plans or specs call for something different, reference them. That keeps the item about the contract, not about taste.
Add a due date. An item with no date has no deadline. Give each one a date that gives the trade a fair chance and keeps the job moving.
How do you get subcontractors to close their punch list items?
Send each sub only its own items, with photos and a due date, then follow up on a regular schedule. When a sub says an item is done, someone from the general contractor checks it in person before you close it. Never close an item on the sub's word alone.
Make it easy to start. A sub should open the list and see its items, where they are and what is wrong. A long list that mixes every trade gets ignored.
Follow up on a rhythm. A short check-in on a set day each week keeps items from going quiet. Walk the open items, not the whole job.
Separate done from closed. The sub marks an item ready. The superintendent confirms it and closes it. Two steps keeps the record honest. If it is not right, send it back with a note and a new photo.
Check the fix, then check what the fix touched. A repaired wall may need paint. A moved fixture may leave a patch. Look at the area around the item before you close it.
Know your leverage. Your contract and the subcontract decide what happens when a sub will not finish. That may include holding back payment or having the work done by someone else. Check the contract before you threaten anything.
What happens at sign-off and closeout?
Once every item is fixed and verified, the owner or architect signs off, usually on the final list. That signed list becomes part of the closeout record. Final payment and retainage release usually follow, on the terms in your contract. Warranty claims after turnover are a separate process.
Get the list signed. A final list with a signature and a date shows what was found, what was fixed and who accepted it. Keep it with your closeout documents.
Retainage. Owners commonly hold back part of each payment until the work is complete. When it is released, and what must happen first, is set by your contract. Punch list completion is often one of the conditions, but check yours. Do not assume.
Closeout paperwork. Finishing the punch list is rarely the last step. The contract may also require as-built drawings, manuals, warranties, lien waivers and other documents. Start gathering them early.
Punch items versus warranty items. A punch item is something wrong or unfinished at turnover. A warranty item is something that goes wrong after turnover, during the warranty period. The warranty terms, including when the period starts and how long it runs, are in your contract. Keep the two lists separate so a callback after turnover does not get mixed into the original list.
What are the most common punch list mistakes?
The most common mistakes are starting too late, writing vague items, mixing trades on one line, skipping photos, closing items without checking them, letting new items appear without dates, and keeping the list in several places. Each one makes closeout slower and harder to defend.
- Starting the list at the last minute, when trades have already left.
- Vague items like "touch up paint" with no location.
- Several trades on one line, so nobody can close it.
- No photos, so the argument is about memory.
- Closing items on a sub's word without looking.
- Adding items after the walk with no date.
- Keeping the list in a text thread, a spreadsheet and a notebook at once.
- Treating warranty callbacks as part of the original list.
Can you run a punch list from your phone?
Yes. A phone already has the camera you need on a walk. The goal is to capture each item once, with a photo, and send it to the right trade. A paper list or a spreadsheet works too, but a phone avoids retyping notes and photos later.
PunchLog is a construction punch list app for iPhone. Superintendents log defects with photos and markup, pin them to floor plans, and assign them to subcontractors. Subcontractors mark items ready, and the superintendent closes them. It works with no signal, syncs when it's back, and exports PDF reports with signature lines. Free while in beta.