What to Include in a Punch List (and How to Write Each Item)
By Eli Vidyaev, superintendent ·
I'm a superintendent in New York City. I've spent 20+ years in ultra-luxury residential construction, and I built PunchLog, a punch-list app. This is what I'd put on every item, with or without an app.
A punch list is the list of items still to fix, finish or correct before a job is accepted. It starts when the work is close enough to done that you can walk it, and it ends when every item is closed and the owner signs off. On the formal side, AIA Document G704-2017, Certificate of Substantial Completion, is the standard form for recording the date the work reaches substantial completion; that date starts warranty periods and lets the owner occupy the work (source: AIA Contract Documents, aiacontracts.com, G704-2017). The list of items still to finish is what usually travels with it.
The fields every item needs
If an item is missing one of these, it comes back to bite you.
- Number. One running number per job. "Item 14" ends arguments.
- Location. Floor, room, and wall or fixture. "Unit 3B, primary bath, left of vanity" beats "bathroom."
- What is wrong. One sentence, written as the fix: "Touch up paint at door casing," not "paint issue."
- Photo. Mark the exact spot. A circle on a photo takes ten seconds and saves a walk.
- Responsible trade or firm. One name, not "someone."
- Date logged and date due. Without a due date nothing has a deadline.
- Status. Open, ready for review, closed. Keep it to three.
- Who closes it. Usually the superintendent. The sub says it is ready; the super confirms.
Example items
| # | Location | Item (written as the fix) | Trade | Photo | Logged | Due | Status | Closed by / date |
|---|---|---|---|---|---|---|---|---|
| 1 | Unit 3B, primary bath | Re-caulk tub-to-tile joint | Tile | yes | Open | |||
| 2 | Unit 3B, entry | Adjust door to latch cleanly | Carpentry | yes | Open | |||
| 3 | Kitchen | Replace cracked outlet cover at backsplash | Electrical | yes | Open |
Want a ready-made sheet to print or fill in? Download the free punch list template. Either way, the format is rarely the problem. Where the list ends up is.
Group it the way people actually work
Two sorts are worth having:
- By location, floor by floor. This is how you walk it and how you re-check it. It is also how the owner will read it.
- By trade. This is what you hand to each sub so they see only their own items.
If your list can only be sorted one way, you will end up re-typing it for the other. That re-typing is where items get lost.
Mistakes that make a punch list useless
- Vague items. "Fix drywall" means a sub has to call and ask which wall.
- No photo. Two people can describe the same scratch differently.
- Items with no owner. If it is everybody's, it is nobody's.
- A list that never ends. Walk, log, issue the list, then close the round. Items found later go on a second round with a date, not quietly onto the first.
- Treating "done" as the sub's call. The sub says ready. The super checks.
- No record. When someone says "that was never on the list," you want the photo and the date.
Where the list should live
The trouble on most jobs is not the template. It is that the list lives in three places: the spreadsheet in the office, the photos in a text thread, and a paper copy someone re-types after the walk. Pick one place for the list and make sure the field photos land in it. If you carry the list on your phone, check that you can add items in a basement or stairwell with no signal, because that is where plenty of items are.
One option
PunchLog is the app I built for this. Every item starts with a photo you can mark up, you assign it to a sub, and the sub can mark it ready but cannot close it. It works offline and exports a floor-by-floor list or a per-sub sheet as PDF or CSV. It is free while in beta and runs on iPhone: jobsitepunchlog.com. The fields above work fine without it.
Checklist before you hand a list to a sub
- Every item has a location, a fix, a photo and one named owner
- Due dates are set
- The sub receives only their items
- You can see what is still open without walking the job
Next: How to run a punch list walkthrough.